Standard Costing Quiz 1 (20 MCQs)

Quiz Instructions

Select an option to see the correct answer instantly.

1. The direct materials standard costs would not be expressed in
2. Based on the case in the journal, why does the standard raw material cost experience a loss difference?
3. What is a standard cost?
4. A total direct materials variance is analyzed in terms of
5. Which of the following cannot be a reason of unfavorable direct materials price variance?
6. What standard cost variance represents the difference between actual factory overhead incurred and budgeted factory overhead based on actual hours worked
7. When performing input-output variance analysis in standard costing, standard hours allowed is a means of measuring
8. The formula for the labour price variance (LPV) is
9. The total variance is RM35, 000. The total materials variance is RM14, 000. The total labor variance is twice the total overhead variance. What is the total overhead variance?
10. If the actual amount of materials used equals the standard amount of materials that should have been used, the difference between the standard cost and actual cost of materials is called
11. If:the standard direct labor rate was RM10 per hour;the direct labor rate variance amounted to RM450 favorable; andthe actual direct labor cost amounted to RM39, 550.The actual direct labor hours worked were:
12. In producing product AA, 6, 300 pounds of direct materials were used at a cost of $ 1.10 per pound. The standard was 6, 000 pounds at $ 1.00 per pound. The direct materials quantity variance is:
13. Using standard costs
14. A standard that represents the most likely scenario can be referred to as the:
15. ..... cost is used for controlling cost.
16. The investigation of direct materials price variance usually begins in the
17. When using full absorption costing, what cost attendant to an element of production are used in order to compute variances from standard amounts?
18. A document that records the standard cost of a single unit of product is known as
19. ..... is a difference between standard cost and actual cost.
20. A debit balance in the labor efficiency variance indicates that