This quiz works best with JavaScript enabled.
Select an option to see the correct answer instantly.
Correct Answer: D) RM 10.00.
Correct Answer: A) Indirect Expense.
Correct Answer: A) Fixed Cost.
Correct Answer: D) Whenever needed by the managers.
Correct Answer: A) Budgeted direct labour cost per unit.
Correct Answer: D) RM 250.00.
Correct Answer: C) RM 2, 084.38.
Correct Answer: C) Periodic-yes; Perpetual-no.
Correct Answer: A) Operating costing.
Correct Answer: B) Liter.
Correct Answer: B) 14.
Correct Answer: A) RM 24, 000.
Correct Answer: C) Any hours worked that exceed normally scheduled working hours.
Correct Answer: B) Variable cost.
Correct Answer: B) Work in progress.
Correct Answer: D) Proportionality.
Correct Answer: A) RM 10.00.
Correct Answer: C) Both (a) & (b).
Correct Answer: B) RM 600.00.
Correct Answer: A) Control of cost.
Correct Answer: B) Is hard to trace.
Correct Answer: C) Labour hours worked.
Correct Answer: C) RM 4.50 per labour hour.
Correct Answer: D) RM 1, 200.00.
Correct Answer: A) Batch costing.