This quiz works best with JavaScript enabled.
Select an option to see the correct answer instantly.
Correct Answer: D) Re-order quantity.
Correct Answer: B) Short.
Correct Answer: A) Debit side of process account.
Correct Answer: A) Normal cost of normal output.
Correct Answer: B) Increase in volume of production.
Correct Answer: B) Rate of change in composition of labour force during a specified period.
Correct Answer: B) Abnormal.
Correct Answer: B) RM 1, 450.00.
Correct Answer: D) 50%.
Correct Answer: D) Premium.
Correct Answer: C) Margin of Safety.
Correct Answer: D) Works manager's r salary.
Correct Answer: C) Rm66.00.
Correct Answer: A) Supplier.
Correct Answer: C) Batch costing.
Correct Answer: A) Cost plus contract.
Correct Answer: D) RM 30.00.
Correct Answer: B) Progress payment.
Correct Answer: A) P1, 650, 000.
Correct Answer: D) Both B & C.
Correct Answer: A) Selling overhead.
Correct Answer: C) The range over which the company expects to operate during a year.
Correct Answer: B) 4000 units.
Correct Answer: A) Prime cost.